One week to get as much done on the MZ12 as I possibly can.
Goals:
- All electric cabling, cleaned, tested and installed
- All brake lines installed
- All engine coolant lines and radiator installed
- All underhood electric components cleaned and installed
- All underdash electrical components tested and installed, including fuse boxes
- Underdash AC and Heater units rebuilt and installed
- Side mirrors installed
- Roof header installed
- Carpet and rear seats installed
- Window trim installed
- Windscreen wipers, horn and washers work
- Driveshaft installed
- Install exhaust
- Fuel tank rebuilt and installed
- Fill engine with oil
Stretch Goals:
- Engine turns over for first time
- Bumper bars rebuilt and installed
- Windscreens, front and rear installed
- Rear lights installed
- Dashboard completely rebuilt and installed
- External trim installed
Days Plan:
- Cleaning Day - Soda blast everything, and paint any brackets or miscellaneous pieces.
- Wiring day - Check and clean all the wiring, rebuild the engine harness with new connectors
- Fetch day - Get as many necessary spare parts from the MZ11 as I can