• 1
Plans for Sprint Week

One week to get as much done on the MZ12 as I possibly can.

Goals:

  • All electric cabling, cleaned, tested and installed
  • All brake lines installed
  • All engine coolant lines and radiator installed
  • All underhood electric components cleaned and installed
  • All underdash electrical components tested and installed, including fuse boxes
  • Underdash AC and Heater units rebuilt and installed
  • Side mirrors installed
  • Roof header installed
  • Carpet and rear seats installed
  • Window trim installed
  • Windscreen wipers, horn and washers work
  • Driveshaft installed
  • Install exhaust
  • Fuel tank rebuilt and installed
  • Fill engine with oil

 

Stretch Goals:

  • Engine turns over for first time
  • Bumper bars rebuilt and installed
  • Windscreens, front and rear installed
  • Rear lights installed
  • Dashboard completely rebuilt and installed
  • External trim installed

 

Days Plan:

  • Cleaning Day - Soda blast everything, and paint any brackets or miscellaneous pieces.
  • Wiring day - Check and clean all the wiring, rebuild the engine harness with new connectors
  • Fetch day - Get as many necessary spare parts from the MZ11 as I can